Trench for an MV 15 kV cable line

PIWOWARSKI · MV 15 kV

Construction of a 2,350 m MV 15 kV cable line in Bolewice

Our first contract for PIWOWARSKI P.S.A. and proof of pace: 2,350 m of 15 kV MV cable line in Bolewice built in 18 days — from 25 November to 12 December 2024. That averages around 130 m of route a day, in late-autumn conditions. Value of the works: PLN 208,800 net.

ClientPIWOWARSKI P.S.A.
LocationBolewice (gm. Miedzichowo)
Greater Poland Voivodeship
VoltageSN-15 kV
BIGBUD's roleWorks contractor
Net valuePLN 208,800 net
Completion period25 Nov 2024 – 12 Dec 2024
2,350 mMV 15 kV cable line
18 daysfrom start to completion

Reference letter

Reference letter: PIWOWARSKI · 13 Dec 2024
Open the referenceDownload PDF

Signed by: Maciej Piwowarski, Członek Zarządu

The task

A short deadline, the full scope

PIWOWARSKI P.S.A. of Sękowo near Nowy Tomyśl is a contractor working in the power sector. They commissioned us for the task „Budowa linii kablowej SN-15 kV w m. Bolewice na odcinku 2350 m” — construction of a 15 kV MV cable line over a 2,350 m section in Bolewice.

The completion period was 18 calendar days: 25 November – 12 December 2024. The client issued the reference letter the day after the works finished, on 13 December 2024. A few days later, on 16 December 2024, we started a larger contract for the same client — the MV/LV network rebuild across eight villages, including Bolewice again.

For a client, a short deadline usually means fitting into an outage window or the schedule of a larger investment. For the contractor, it means good organisation: machinery, materials and crews must be on site from day one.

  • 2,350 m of MV 15 kV cable line
  • 18 days from start to completion
  • Reference letter issued the day after completion

How the works went

How to build 2,350 m of line in 18 days

A general description of how such a job is organised. The reference letter confirms the scope, dates and value — it does not describe the technology in detail.

  1. 01

    Ready before mobilising

    Route set out, materials — cable, accessories, ducts — ordered and delivered, machinery moved to site. On a short job there is no time to wait for deliveries.

  2. 02

    Parallel fronts

    Trenching, cable laying and backfilling run in parallel on successive sections, so no trench stays open longer than necessary.

  3. 03

    Own machinery

    We have our own CAT excavators, a Volvo HDS truck for cable drums and a drilling rig — so we never have to wait for hired plant.

  4. 04

    Jointing, testing, acceptance

    Finally, cable accessories, tests and measurements, reinstatement and handover of documentation — on time and without defects.

Technology

An MV 15 kV cable line in a nutshell

General information about lines of this kind.

What a 15 kV MV line does

Medium-voltage 15 kV lines distribute power from primary substations (GPZ) to MV/LV transformer substations, which supply customers at 0.4 kV. In many regions of Poland 15 kV is the standard MV network voltage. See MV and LV cable lines.

Three cables, three phases

Modern MV cable lines are usually built from three single-core XLPE-insulated cables — one per phase — laid together in one trench. We describe the cable types in MV cables: XRUHAKXS and NA2XS(F)2Y.

Pace and quality

Speed only makes sense if quality doesn't suffer — especially in joints and terminations, on which the line's service life depends. The reference letter confirms the works were done “properly” and “without defects”. Stages of building a line: From design to acceptance.

What this project shows

A first contract that opened the door to the next

Bolewice was our first job for PIWOWARSKI P.S.A. A short deadline and a clear scope — 2,350 m of 15 kV MV cable line — let the client test us in practice. The outcome was a reference letter issued the day after completion and a further contract, worth almost two and a half times as much, starting four days later.

For general contractors this is an important signal: we can mobilise quickly, keep up the pace and hand over the scope without defects. More on subcontracting with us on the For general contractors page.

  • 18 days for 2,350 m of MV 15 kV line
  • reference letter of 13 Dec 2024 — the day after completion
  • next contract from 16 Dec 2024: network rebuild in 8 villages
„The above-mentioned works carried out by BIGBUD […] were performed properly, in accordance with the terms of the contract and good construction practice, on the agreed dates and without defects.”
PIWOWARSKI P.S.A.reference letter of 13 Dec 2024 (translated from Polish) — Maciej Piwowarski, Member of the Management Board

Got a job with a tight deadline?

Tell us how much time you have — we will check whether we can make it and draw up a realistic schedule.