Medium-voltage overhead line on poles

MV overhead lines

Medium-voltage overhead lines, 6–30 kV

We build and rebuild sections of MV and LV overhead lines, erect poles, make tie-ins to cable lines and remove lines taken out of service. On a single contract for ENEA Operator we dismantled 8.266 km of MV line and 89 pole positions.

What the service covers

Overhead networks still have their place

Despite ongoing undergrounding, overhead lines still make up a large part of Poland's medium-voltage network, especially in rural areas. They are cheaper to build over long open stretches and easy to inspect and repair. In practice the network is mixed: overhead sections pass into cable at poles fitted with terminations, and pole-mounted substations sit alongside ground-mounted ones.

Overhead line work is not only about building new sections. Just as often it means replacing poles, rebuilding a section that conflicts with a new scheme, erecting a cable-to-overhead transition pole, or removing a line after it has been undergrounded. Dismantling needs the same discipline as construction — conductors, fittings, poles and foundations all have to come out.

For pole and conductor work we use our own plant: a Volvo truck with a loader crane to transport and set components, CAT excavators to dig for foundations and a Tesmec hydraulic puller.

  • Erection and replacement of MV and LV poles
  • Transition poles with cable terminations — tie-ins to cable lines
  • Removal of overhead lines, poles and pole-mounted transformer substations
Volvo lorry with a loader crane on a network construction site
Volvo FE with loader crane — BIGBUD's own plant

Scope of works

What we do on overhead lines

MV and LV poles

Excavation and foundations, setting poles with the loader crane, fitting steelwork, crossarms and insulators as designed.

Conductors

Stringing and sagging conductors on rebuilt sections, maintaining the required sags and clearances.

Rebuilds

Rebuilding line sections where they conflict with roads, buildings or other networks. More: utility conflict relocation.

Cable-to-overhead tie-ins

Poles with outdoor terminations, surge arresters and fittings for the transition from overhead line to cable.

Dismantling

Removing conductors, poles, foundations and pole-mounted substations; taking material away and restoring the land.

Acceptance

Measurements, reports, as-built geodetic survey and the documentation required by the operator.

How the works run

How we carry out overhead line work

01

Design check

We check pole positions, plant access, conflicts with trees, roads and other networks and the extent of dismantling on site.

Scope of works

  • site visit
  • access assessment
  • materials schedule

Result

  • programme and delivery plan
02

Arrangements and outages

We agree outage dates and the way the work area will be made safe with the operator, and access with the landowners.

Scope of works

  • notifications
  • outage programme
  • traffic management next to roads

Result

  • approved work plan
03

Excavation and foundations

We excavate for poles and foundations — with CAT excavators, or by hand where the ground requires it.

Scope of works

  • setting out pole positions
  • excavation
  • foundations

Result

  • positions ready for poles
04

Poles, fittings and conductors

We set the poles with the loader crane, fit steelwork and insulators, string and sag conductors and make tie-ins to cable lines.

Scope of works

  • setting poles
  • fitting hardware
  • stringing and sagging

Result

  • complete line section
05

Removing retired sections

Once supply has been switched over we take down old conductors, poles and pole-mounted substations and restore the land.

Scope of works

  • removing conductors
  • removing poles and foundations
  • material removal

Result

  • land restored
06

Testing and documentation

We carry out measurements, compile the reports and the as-built geodetic survey and hand the line over for operation.

Scope of works

  • acceptance measurements
  • geodetic survey
  • as-built documentation

Result

  • acceptance report

Technical solutions

Typical components of MV and LV overhead lines

Indicative only — the actual solutions are set by the design and the operator's standard.

ComponentTypical solutionsNotes
PolesSpun and prestressed concrete poles, single and composite structures (terminal, angle, section)Pole type depends on its function in the line and the loads
MV conductorsBare AFL conductors and covered (insulated-sheath) conductorsCovered conductors are used in wooded areas, among others
LV conductorsAerial bundled cablesStandard on modern 0.4 kV networks
InsulationPin, suspension and long-rod insulatorsChosen by voltage and pole function
Cable tie-insPole with outdoor terminations, surge arresters and a switch-disconnectorTransition from overhead line to cable
Pole-mounted substationsMV/LV transformer substations on polesOften replaced by ground-mounted units when a line is undergrounded — MV/LV substations

Safety and organisation

Working on a network that has to keep running

Most overhead line work takes place on a network that customers rely on. Planning is therefore essential: the order of works and the outage and switching dates are set by the operator, and the contractor has to be ready to complete everything planned within the outage window. Every work area is prepared and handed over in line with the operator's procedures.

Logistics matter when dismantling, too: recovered conductors, insulators, poles and substation components must be sorted, removed and handed over as set out in the contract. On long stretches through farmland and forest, plant access and minimising crop damage are important — we plan the work together with landowners.

Staff working on power equipment hold the qualifications required by law for this type of work. The safety principles we follow are described on our Safety and quality page.

Project

Building and removing overhead network for ENEA Operator

In the Niegosławice municipality we erected 2 MV poles and 1 LV pole and, once the new cable lines were in service, removed 8.266 km of MV overhead line, 89 MV pole positions, 4 LV pole positions, 90 m of LV overhead line and 3 pole-mounted transformer substations.

„The works were performed with due care, in accordance with the terms of the contract and the applicable technical requirements.”
ENEA Operator sp. z o.o., Zielona Góra Distribution Branchreference dated 13 Aug 2026 (translated from Polish) — Michał Jankowiak, Head of the Investment Department

Photos

From our sites

Questions

Overhead lines — frequently asked questions

Which overhead line voltages do you cover?

We focus on medium-voltage lines of 6–30 kV and low-voltage 0.4 kV networks. For work at other voltages, please get in touch and we will discuss the scope individually.

Do you take on dismantling only?

Yes. Removing lines, poles and pole-mounted substations can be a separate order — for example after undergrounding carried out by another contractor. On the ENEA Operator contract the dismantling covered 8.266 km of MV line and 89 pole positions.

Do you work near live networks?

We work under the arrangements agreed with the operator — with the section switched off and made safe, or at a safe distance from live parts. Outage dates are always set by the operator.

What plant do you use to erect poles?

We have a Volvo FE 320 truck with an HMF 2120 loader crane, CAT excavators and a Tesmec ARS405 hydraulic puller. The full list is on our equipment page.

Do you build complete new overhead lines?

Yes, at MV and LV. Our references to date relate mainly to cable lines, the erection of individual poles and the removal of overhead lines — so we always discuss the scope of a new contract individually.

A line to rebuild or remove?

Describe the scope or send the design — we will prepare a quote and a programme that allows for outages.