Wind turbine against the sky

Services · Renewable energy

Wind farms — internal MV network and grid connection

Wind turbines often stand kilometres apart and far from the point of connection. They are linked by an underground medium-voltage cable network running across fields, roads and ditches. We build that infrastructure — from the lines between turbines to the connection with the MV switchgear of the grid substation.

Our role

Kilometres of MV cable in open country — our speciality

Each wind turbine has its own transformer that steps the generator voltage up to medium voltage. Turbines are connected with MV cables into strings, and the strings run to MV switchgear at a collection point — on smaller farms a junction or switching station connected to the operator's MV network, on larger ones a customer substation (in Polish: GPO) where the power is transformed up to high voltage.

For a contractor this means long cable routes across farmland, numerous crossings with local roads, drainage ditches and other utilities, dozens of joints and terminations and rigorous acceptance testing. These are exactly the works we carry out on MV lines for operators — with our own GRUNDODRILL 15 XPT drilling rig, CAT excavators and a Tesmec ARS405 puller for cable pulling.

In fairness: our reference letters do not yet include a completed wind farm. What we show instead are contracts with long MV cable lines — including 3 × 5,715 m of cable for ENEA Operator and a 5,725 m 15 kV line with around 600 m of drilled crossings in Toruń — because they best reflect the scale of work on a wind farm network.

  • MV cable network linking turbines into strings
  • Lines to the MV switchgear of the HV/MV substation or to the operator's network
  • Drilled crossings under roads, ditches and watercourses
  • Joints, terminations, acceptance testing and as-built survey
Wind farm at sunset
Wind farm — illustrative photo

The developer's path

A wind farm's route to grid connection — in brief

Connecting a wind farm is a multi-year process, and its details depend on the operator, capacity and voltage level. In outline:

  1. 01

    Connection conditions

    The developer applies to the distribution system operator (or, for large capacities, the transmission operator) for connection conditions; the operator assesses the network's capacity and issues the conditions or refuses.

  2. 02

    Connection agreement

    The agreement sets out the point of connection, the works on the developer's and operator's side and the programme.

  3. 03

    Design and permits

    Designing the farm, its internal network and the grid substation, agreements with the operator, and the decisions and permits the scheme requires.

  4. 04

    Construction

    Turbine foundations and erection, access roads, the grid substation and the MV cable network — the last of these is where we work.

  5. 05

    Testing and acceptance

    Cable tests and measurements, as-built documentation, survey and acceptance by the operator.

  6. 06

    Energisation

    Turbine commissioning, the tests required by the operator and the remaining formalities — including with the Energy Regulatory Office (URE) — after which the farm starts generating.

Connection elements

A wind farm's electrical infrastructure

Typical MV elements of a wind farm and what we do on them:

ElementFunctionBIGBUD's scope
Turbine transformer and MV switchgear in the towerSteps the generator voltage up to MV; usually supplied with the turbineBringing in and connecting the MV cables, terminations, testing
Internal MV cable networkLinks turbines into strings and takes them to the collection pointTrenching, drilling, MV cable laying, joints, route marking
MV junctions and switchgearSplitting and connecting strings, ownership boundariesSetting junctions, fitting out, connections
Customer HV/MV substation (GPO) with MV switchgearCollects power from the strings and transforms it to HV on larger farmsMV cable lines to the substation's MV switchgear; HV works are done by specialist contractors
Line to the operator's substation / DSO networkLinks the farm to the operator's network at the point of connectionIn the MV option — building the cable line and the tie-in agreed with the DSO
Ducts and SCADA fibreCommunication between turbines, substation and the control systemDucts and cable ducting in the shared trench with the MV cables

How the works run

How we build a wind farm cable network

01

Design and route review

We review the network design, connection conditions and the route on the ground: soils, crossings, land access and the order in which turbine bases are released.

Scope of works

  • Document review
  • Site visit
  • Drilling plan

Result

  • Quotation and programme
02

Procuring cables and accessories

We plan drum lengths to keep the number of joints down and order accessories to match the cables.

Scope of works

  • Cable length planning
  • Purchase orders

Result

  • Drum delivery plan
03

Trenching and drilling

We trench across farmland and drill under roads, ditches and watercourses, coordinated with the road and foundation works.

Scope of works

  • Machine trenching
  • HDD crossings
  • Protective ducts

Result

  • Route ready for cable
04

Cable laying and jointing

We pull cable off the drums with a puller, make straight joints and terminations, and connect turbines and junctions.

Scope of works

  • Laying MV cables
  • Joints and terminations
  • Connections

Result

  • Cable strings ready for testing
05

Backfill and reinstatement

We backfill with route marking and restore farmland to the condition agreed with the landowners.

Scope of works

  • Backfill and compaction
  • Land restoration

Result

  • Land back in use
06

Testing, records, acceptance

We carry out cable acceptance tests, the as-built survey and the documentation needed for acceptance and commissioning of the farm.

Scope of works

  • Voltage tests and measurements
  • As-built survey
  • Documentation

Result

  • MV network ready for energisation

Photos

From our sites

FAQ

Wind farms — frequently asked questions

Do you build 110 kV customer substations?

Our speciality is medium- and low-voltage networks. On a farm with its own HV/MV substation we build the MV cable lines and connections to the substation's MV switchgear; the high-voltage part is delivered by specialist contractors.

Have you completed wind farms before?

Our reference letters do not yet include a completed wind farm. They cover long MV cable lines, drilling, junctions and MV/LV substations on operators' networks — the works a farm's internal network is made of. Full letters: References.

What cables are used in a wind farm network?

Usually single-core MV cables with aluminium conductors and cross-linked polyethylene insulation, sized for the string's capacity and route length. The type and size are always set by the design. More in MV cables: XRUHAKXS and NA2XS(F)2Y.

How do you cross roads and ditches on the cable route?

By directional drilling with our own GRUNDODRILL 15 XPT rig, pulling in a protective duct. Across our contracts we have completed around 1.5 km of drilled crossings and pipe jacking. See horizontal directional drilling.

Can you work in parallel with turbine erection?

Yes — that is the usual situation. We agree the cable-laying programme with the general contractor so it does not clash with turbine component deliveries and crane work.

Do you work anywhere in Poland?

Yes. Our office is in Kraków and we move our plant with our own transport — including to sites in northern and western Poland, where most wind farms are being built.

Planning a wind farm cable network?

Send us the MV network design and the connection conditions — we will quote with a works programme.